Toothed roller crusher is equipment, suitable for coal, metallurgy, Vertical Mill Bearing Lubrication , chemical industry, building materials and other industries. It is more suitable for crushing raw coal (including vermiculite) in large coal mines or coal preparation plants. Installation and maintenance The maintenance of the machine is an extremely important recurring task. It should be closely coordinated with extreme operations and maintenance. Full-time personnel should perform on-duty inspection. Maintenance of the machine 1. The shaft bears the full load of the machine, so good lubrication has a great relationship with bearing life. It directly affects the service life and operating rate of the machine. Therefore, the injected lubricant must be clean and the seal must be good. The main oiling places of this machine (1) rotating bearings (2) roll bearings (3) all gears (4) movable bearings, sliding planes. 2. The newly installed rims are prone to loosening and must be checked frequently. 3. Pay attention to whether the parts of the machine work normally. 4, pay attention to check the wear degree of easy-wearing parts, pay attention to replacing worn parts at any time. 5. The plane of the bottom frame of the movable device should be out of dust and other materials to prevent the movable bearing from moving on the bottom frame when the machine encounters unbreakable materials, resulting in serious accidents. 6, bearing oil temperature rise, should immediately stop the inspection to eliminate the cause. 7. If there is an impact sound when turning the gear during operation, it should be stopped immediately for inspection and eliminated.
Installation test run 1. The equipment should be installed on a horizontal concrete foundation and fixed with anchor bolts. 2. When installing, pay attention to the main body and the vertical. 3. After installation, check whether the bolts in all parts are loose and whether the main engine compartment door is fastened. If so, tighten it. 4. Configure the power cord and control switch according to the power of the device. 5. After the inspection is completed, carry out a no-load test run, and the test run can be carried out normally.